How long will it take to install the asphalt?

The record for Jackson Asphalt is 450 ton is one day or 3500sqm.

Driveway 500m2 is generally half a day to complete (depends on many factors such as shape, access, distance to plant etc)

Carpark 2000m2 is generally one day to complete (depends on many factors such as shape, access, distance to plant etc)

Hardstand 2500+m2 per day (depends on many factors such as shape, access, distance to plant etc)